An importance milestone of Ben Luc – Long Thanh expressway In the 19 December morning, the Vietnam Expressway Corporation held the Inauguration Ceremony of Binh Khanh bridge, the major work of Package J1 under Ben Luc – Long Thanh expressway project. This is an important milestone after years making efforts to solve the difficulties in […]
Project name: CONSTRUCTION OF BRIDGES ON THE COASTAL ROAD CONNECTING AN BIEN – RACH GIA CITY Package: Package No. 06: Construction of bridges on the coastal road connecting An Bien – Rach Gia city Location: Tay Yen commune, An Giang province Employer: Department of Construction of An Giang province Main contractor: VNCN Engineering Construction […]
Project: Plant of waste classification, waste disposal, producing biogas and organic mineral fertilizers Construction Item: Fermentation Tank including heat piping system Location: Bo Trach – Quang Binh Construction period: 08/2017 – 01/2018 The project for plant of waste classification, waste disposal, producing biogas and organic mineral fertilizers, with a total investment of 1300 billion, was […]
Project: Damen Song Cam Shipbuilding Construction Item: Warehouse No.2 and concrete yard 4.5tons Location: Thuy Nguyen – Hai Phong Construction period: 10/2017 – 4/2018. Warehouse No.2 Project belongs to Damen Song Cam Shipbuilding which was previous constructed by Vinaconex E&C and already handed-over to the Employer for services. The warehouse No.2 is constructed in […]
- Location: Hanoi
- Employer Level 1: Hanoi Construction Coporation (HANCORP)
- Employer Level 2: Vietnam Construction and Engineering JSC (Vinaenco)
- Supervision Consultant: ARTELIA International- French Republic
- Construction period: 8 / 2011-2017.
Project: New Horizon
- Employer: Vietnam Engineering and Construction JSC - VINAENCO
- Construction location: Hanoi, Vietnam
- Construction period: 2014-2016
- Main Contractor: Vinaconex E&C