Employer: Project Management Unit No.85 (PMU85)
Funding: Japan International Cooperation Agency (JICA) + counterpart fund
Location: Hanoi, Vietnam
Construction period: From September 2011 to December 2014


Employer: Project Management Unit No.85 (PMU85)
Funding: Japan International Cooperation Agency (JICA) + counterpart fund
Location: Hanoi, Vietnam
Construction period: From September 2011 to December 2014

Employer: Vietnam Expressway Corporation (VEC)
Funding: Asian Development Bank (ADB) + counterpart fund
Location: Ho Chi Minh City, Vietnam
Construction period: 36 months

Employer: Vietnam Expressway Corporation (VEC)
Funding: Asian Development Bank (ADB) + counterpart fund
Location: Long An Province and Ho Chi Minh City, Vietnam
Commencement: May 2015
Completion (planned): May 2018

Employer: Vietnam Expressway Corporation (VEC)
Funding: Japan International Cooperation Agency (JICA) + counterpart fund
Location: Quang Nam Province, Vietnam
Construction period: 36 months
Commencement: May 2014

Employer: Quang Ngai Department of Transport
Funding: Government’s Bonds
Location: Quang Ngai Province, Vietnam
Construction period: January 2014 – October 2015
Contractor: Vinaconex E&C

Funding: Asian Development Bank (ADB) + counterpart fund
– Location: Dong Thap Province, Vietnam
– Construction period: 43 months
+ Commencement: March 2014
+ Completion (planned): October 2017

On 11th December 2015, Vinaconex E&C is among Enterprises who honorably received President Commendation from the President of the Japan International Cooperation Agency (JICA) in recognition of its outstanding contribution to the development of society and the economy of the country. VINACONEX E&C had undertaken and successfully completed construction project of Nhat Tan Bridge (Vietnam-Japan […]

Since 22nd December 2009, Vinaconex E&C is awarded to become the main contractor of Package A8, NoiBai – LaoCai Highway Project. The Package value is VND 1,677 billion under funded by loan of Asian Development Bank (ADB). Employer of the Project is Vietnam Expressway Corporation, Ministry of Transport. Package A8 has alignment length of 26km […]

VINACONEX E&C has participated in the Joint venture Contractor to execute the Works for the Package 2 – Construction of section from Soc Son to Thai Nguyen of New National Highway No.3 under Regional Road Network Construction Project. The Package 2 PK2 works consist of construction of expressway from Km.29+600 to Km.61+313, include 4 […]

Vinaconex E&C was selected to be the contractor to perform Construction Work of Vietnam Stanley New Factory phase 1. The Factory is located at Duong Xa Commune, Gia Lam district, Hanoi, Vietnam. The Construction Work includes 8,200 square meter of main Workshop and 4,650 square meter of Office and shall be performed from November 2009 […]