About Us

Web links


Online
  • Online : 1
  • Visitor :


VINACONEX E&C performs the package NIP/CP-11

The package is a part of  the project of rehabilitation and improvement of national highway network that belongs to Ministry of Transportation of Vietnam. So far, VINACONEX E&C will perform construction from Km 149+460 to KM 173+438 with total length is 23.8 km, including 7 cast-in-situ RC bridges. Contract value is estimated 295 Billion VND and Construction Schedule is  24 months.