Contract value: US$ 26 million included two Package CV1 - US$ 23.7 million and Temporary facility package - US$ 2.3 million Construction period : From Mar 2006 to Feb 2009
Location: 194 Tran Quang Khai Str, Hoan Kiem Dist, Ha Noi, Viet Nam.
Client: Bank for Investment and Development of Viet Nam(BIDV).
Construction period: From August 2006 to March 2007.
Client: Nissei Vietnam Co., Ltd.
Location: Phuc Dien Industrial Zone, HaiDuong, Vietnam.
Area: 60,000 sq.m
Construction period: From August 2006 to March 2007
Client: Brother Vietnam Co., Ltd.
Location: Phuc Dien Industrial Zone, HaiDuong, Vietnam
Area: 160,000 sq.m
Construction period: From June 2006 to January 2007.