Location: 194 Tran Quang Khai Str, Hoan Kiem Dist, Ha Noi, Viet Nam.
Client: Bank for Investment and Development of Viet Nam(BIDV).
Construction period: From August 2006 to March 2007.
Scope of work:Construction of substructure for the Building 25 floors of BIDV Head office in Ha Noi, Namely includes about 4800m of cast-in-situ piles 1500mm diameter; 680m2 of earth retaining wall 800mm thickness; and 3 sub-basements with total 5800m2 of floor.
Client: Bank for Investment and Development of Viet Nam(BIDV).
Construction period: From August 2006 to March 2007.
Scope of work:Construction of substructure for the Building 25 floors of BIDV Head office in Ha Noi, Namely includes about 4800m of cast-in-situ piles 1500mm diameter; 680m2 of earth retaining wall 800mm thickness; and 3 sub-basements with total 5800m2 of floor.