About Us

Web links


Online
  • Online : 1
  • Visitor :


Signing construction contract of package no. 8: Improvement of National Highway no. 38B-2 Section Trang Bridge-Hung Yen town

According to the signed contract, VINACONEX shall undertake package no.8 with total length of 19.249km, in which the key items encompass: 4 upgrade intersections, 5 box culverts, 31 pipe culverts and 4 small bridges ( Quan Do bridge, Cho Dau bridge, An Tao bridge, Pho Giac bridge). Contract value is 240.39 billion dong, with construction progress of 24 months, scheduled to completed on April 2010. 

SMEC-ROUGHTO and APECO shall be Supervisor Consultant at the project. VINACONEX Corporation authorized VINACONEX E&C to manage this contract.

1 2