In the morning of December 31st, 2022, the Ministry of Transport in coordination with People’s Committee of Quang Tri Province and People’s Committee of Thua Thien – Hue Province organized the Inauguration and Traffic Opening Ceremony of Cam Lo – La Son Expressway. Cam Lo – La Son Expressway is one […]
- . Package Civil works: Construction of the entire route (including survey and design of shop-drawings)
- . Location: Cai Rang district, Can Tho City; Chau Thanh, Phung Hiep district and Vi Thanh district and Hau Giang province.
- . Employer: Project Management Unit My Thuan
- . Contractor: Truong Son – 36 – CC1 – VNCN E&C – Tan Nam Joint Venture
- . Contract value: VND 7,555 billion
- . Contract value: VND 7,555 billion
- . Employer: Ho Chi Minh City Finance and Investment State-owned Company
- . Location: 33 – 35 – 37 – 39 Pasteur Street, Nguyen Thai Binh Ward, District 1, HCM City
- . Package: Construction and Installation Works for “HFIC Office and High-rise Building”
- . Funding: HFIC’s Investment and Development Fund
- . Implementation Period: 20 months/496 days
Vinh Hao – Phan Thiet section is adjacent to the starting point of Phan Thiet – Dau Giay expressway sub-project, is in Binh Thuan province where the natural conditions and climate are extremely harsh. Contract Package XL04 was commenced in December 2020 with 24 months for completion. This has been a […]
My Thuan – Can Tho expressway is approximately 23 kilometers long. The Project has the total investment of VND 4,800 billion with the Ministry of Transport is the Employer and Cuu Long Corporation for Investment Development and Project Management of Infrastructure (My Thuan Project Management Unit now) is the project management entity.
Vinh Hao – Phan Thiet Expressway Section under the Eastern North – South Expressway Construction Investment Project for the 2017 – 2020 period has the total length of 100.82km, passes through 4 districts in Binh Thuan province. This Section starts at Km134 in Vinh Hao commune, Tuy Phong district, Binh Thuan province
Tan Thang Cement Plant Investment Construction Project (Chain 1) has rotary kiln capacity of 5,000 tons of clinker/day equivalent to 1.96 million tons of cement/year. This Project was granted the Certificate of Investment No. 27111000010 by the People’s Committee of Nghe An Province
Long Son Petrochemicals – LSP is the first petrochemical complex in Vietnam having capacity up to 1.6 million tons/year which will produce substitutes for imported polyolefins. The Project also includes other infrastructures apart from the petrochemical complex and a deep-water port.
Tan Thang Cement Plant Investment Construction Project (Chain 1) has rotary kiln capacity of 5,000 tons of clinker/day equivalent to 1.96 million tons of cement/year. Investor: Tan Thang Cement Joint Stock Company. Contract No. 20180505 / XL01 /XMTT- LILAMA-VINACONEX E&C (now VNCN E&C) was signed on 05 May 2018 by LILAMA – VNCN E&C for […]
The high-tech fruit and juice processing plant has a planned area of 14.03 hectares, of which 4.9 hectares has been handed over for processing fruits and juices. The project has a total investment of VND 1,200 billion, divided into 2 phases