In 24 December 2023, the Ministry of Transport held the Inauguration Ceremony of 4 major transport projects including My Thuan 2 bridge.
- . Project: NORTH – SOUTH EXPRESSWAY CONSTRUCTION PROJECT (BEN LUC – LONG THANH SECTION)
- . Package: PACKAGE J1 CIVIL WORKS (KM21+739.5 – KM24+503) BINH KHANH BRIDGE AND APPROACH
- . Employer: VIETNAM EXPRESSWAY CORPORATION (VEC)
- . Contractor: SHIMIZU – VNCN E&C JOINT OPERATION
- . Funding: Official development assistance fund from Japan International Cooperation Agency (JICA)
- . Construction period: The time for implementing the Contract is 47 months; The time for resumption and completion of the Package is estimated 24 months.
- . Contract Package: Construction of project component 2, NH.14H connecting road, section Km0+00 – Km11+400
Location: Quang Nam province - . Client: People’s Committee of Quang Nam province
- . Representative of the Client: Project Management Board of Transport Works Construction Investment of Quang Nam province
- . Construction Contractor: Joint Venture of VNCN Engineering Construction and Investment Joint Stock Corporation – M.E.I Material, Equipment & Investment Construction Joint Stock Company – Anh Duong Company Limited.
- . Contract value: VND 173,645,137,000
- . Implementation period: 720 days (from 16/9/2023)
- . Contract Package No. 14: Shop-drawing design – cost estimate and construction of section Km0+000 ~ Km16+000
- . Location: Dong Thap province
- . Client: People’s Committee of Dong Thap province
- . Representative of the Client: Transport Works Construction Investment Project Management Board of Dong Thap province
- . Construction Contractor: Joint Venture of VNCN Engineering Construction and Investment Joint Stock Corporation – Thien An Construction and Mechanical Company Limited – Dacinco Construction Investment Limited Company
- . Contract value: VND 2,805,790,749,000
- . Implementation period: 28 months (from 25 June 2023)
- . Contract package No. 18: Construction of Line 2 (including traffic safety security cost and other related costs) – Phase 1
- . Location: Ha Nam province
- . Client: Construction Investment Project Management Board – Ha Nam province
- . Construction Contractor: VNCN Engineering Construction and Investment Joint Stock Corporation (VNCN E&C)
- . Contract value: VND 769,609,925,000
- . Implementation period: 18 months
- . CONTRACT PACKAGE XL09 : Construction of Ring Road No. 3, Binh Chanh District Section (Km69+978 – Km78+100)
- . LOCATION : Binh Chanh District, Ho Chi Minh City.
- . EMPLOYER : People’s Committee of Ho Chi Minh City.
- . REPRESENTATIVE OF EMPLOYER : Transportation Works Construction Investment Project Management Authority.
- . CONTRACTOR : Joint Venture of VNCN Engineering Construction and Investment Joint Stock Corporation – Hai Dang Joint Stock Company – Hong An Road and Bridge Construction Service Trade Company Limited – 236 Traffic Project Construction and Management Joint Stock Company – Material Equipment and Civil Engineering Joint Stock Company 624
- . CONTRACT VALUE : VND 2,258 billion
- . IMPLEMENTATION PERIOD : 33 months
- – Package XL01: Km285+000 ÷ Km337+500
- – Location: Khanh Hoa province
- – Employer: Project Management Unit 7
- – Main Contractor: Lizen Joint Stock Company – Phuong Thanh Transport Construction and Investment Joint Stock Company – Hai Dang Joint Stock Company – VNCN Engineering Construction and Investment Joint Stock Corporation (Lizen – Phuong Thanh – Hai Dang – VNCN E&C Joint Venture).
- – Contract value: 4,701 billion VND
- – Implementation period: 34 months
- – Package XL-02: Construction of Km91+800 – Km114+200 (including survey and design of shop-drawings).
- – Location: Kien Giang province and Ca Mau province.
- – Employer: Project Management Unit My Thuan
- – Main Contractor: VNCN Engineering Construction and Investment Joint Stock Corporation – 620 Infrastructure Development and Investment Corporation – Hai Dang Joint Stock Company – Thi Son Production and Construction Company Limited Joint Venture (VNCN E&C – 620 IDIC – Hai Dang – Thi Son Joint Venture).
- – Contract value: 3,717 billion VND
- – Implementation period: 34 months
- . Package CW2: Construction of Km5+000 ~ Km10+000 and Km12+600 ~ Km13+750)
- . Location: Dong Nai province and Ho Chi Minh City
- . Employer: Project Management Unit My Thuan (PMU My Thuan)
- . Main Contractor: Dongbu (Korea) – VNCN E&C (Vietnam) Joint Venture
- . Contract value: 12,586,020,928 KRW and 937,162,483,909 VND
- . Implementation period: 28 months (from the issuance of NTP)
In the morning of December 31st, 2022, the Ministry of Transport in coordination with People’s Committee of Quang Tri Province and People’s Committee of Thua Thien – Hue Province organized the Inauguration and Traffic Opening Ceremony of Cam Lo – La Son Expressway. Cam Lo – La Son Expressway is one […]