GMS Ben Luc – Long Thanh Expressway Project, Package A3: Km16+600 – Km18+713.5

– Employer: Vietnam Expressway Corporation (VEC)
– Funding: Asian Development Bank (ADB) + counterpart fund
– Location: Ho Chi Minh City, Vietnam
– Construction period: 36 months
+ Commencement: May 2015
+ Completion (planned): May 2018
– Contractor: Joint Venture of Halla Corporation – Vinaconex Engineering Construction and Investment Joint Stock Company (Halla – Vinaconex E&C Joint Venture)
– Contract value: 732 billion VND
– Scope of works:
+ Total length of the package: 2.11km. Starting point is at Km16+600 in Binh Chanh District and End point is at Km18+713,5 in Nha Be District, Ho Chi Minh City
+ Construction of 02 large bridges (total length of 1,952m) including:
a) Ba Lao Bridge (690m) over Can Giuoc river includes 12 super-T girder spans (9 girders on each span) and a cantilever continuous-span frame bridge constructed by box-girder with the various heights of box girder.
b) Viaduct No.1 (1,262m) crossing Le Van Luong Street and Long Thoi – Nhon Duc Street includes 23 super-T spans (9 girders on each span) and 2 continuous-span frame bridges casted-in-situ with the fixed height of box girders.
+ Construction of 160m road.
+ Soft soil treatment with PVD, SBD, DMM, reinforced concrete piles 30x30cm.